Fabrication and Installation

FABRICATION / INSTALLATION / EQUIPMENT SUPPLY / TRANSPORTATION

Warrikal were engaged by the client to complete the full supply, civil and mechanical scope of works prior to

operational shutdown as a high priority, due to the current conveyor belt wear and changeout requirements. Works were performed safely, successfully and on schedule.

  • Work hours: 14,500
  • Supply of all steel work for both conveyors –approximately 90t
  • Transport to site of all items – approx. 30 trailers
  • All excavations, formwork, reinforcing steel and concrete supplied and completed as part of the civil scope.
  • Safe & risk assessed installation of multiple structures over live conveyors.
  • Supply of all equipment required.

 

Key Highlights:

  • Full quality control and assurance of project from beginning to completion. 
  • All works completed on time and on budget. 
  • Zero incidents, accidents or near misses 
  • Rapidly expedited time frame for Warrikal to complete procurement, fabrication, mobilise to site and successfully complete the works. 

contact us

We excel in delivering fixed plant reliability ensuring consistent
results day in day out

For all enquiries, please complete the form below and we
will be in touch soon.

(08) 6102 3733

Level 2, 30 Dehli Street, West Perth,
WA 6005
enquiry@warrikal.com.au