EARTH WORKS / INSTALLATION OF GEOMEMBRANE / INSTALLATION OF SLEEPERS / CONCRETE WORKS

The project aimed to repair and update Evaporation Ponds in the Acid Rock Drainage Facility to reduce seepage, enhance pond integrity, and provide operational and environmental improvements.

 

The scope of work included the following:

  • Rip, moisture condition and compact existing subgrade within each EP 2 and 3
  • Construct embankment widening sections within the southern corners of EP 2 & 3
  • Excavate anchor trenches for the BGM liner
  • Place and weld BGM liner on the surface of the EP floor, on batter slopes and install
  • Backfill anchor trenches for the BGM liner including backfill of anchor trench on the southern crest
  • Reinstall the Southern Header Discharge Pipe on the Southern crest of the EP2 & 3, including fixing of the pipelines
  • Installation of access track crossing

Key Highlights:

  • Earthworks and subgrade preparation to 250,000m2
  • Installation of 250,000 m2 of BGM Geomembrane
  • Installation of 3,500 + sleepers
  • Completion of Southern header concrete works

contact us

We excel in delivering fixed plant reliability ensuring consistent
results day in day out

For all enquiries, please complete the form below and we
will be in touch soon.

(08) 6102 3733

Level 2, 30 Dehli Street, West Perth,
WA 6005
enquiry@warrikal.com.au